Australian data center operator NextDC's shares plunge 40% after it slashes earnings forecast

Advertisements


The logo of Australian data centre operator NextDC is seen on its Artarmon facility in Sydney on September 15, 2026. (Photo by Saeed KHAN / AFP via Getty Images)

Saeed Khan | Afp | Getty Images

Shares of Australia’s NextDC plunged 39.5% on Wednesday after the data center operator slashed its annual earnings forecast, citing power supply delays at its Melbourne facility amid local community and stakeholder opposition.

The company lowered its fiscal 2027 revenue guidance to between $475 million Australian dollars and A$500 million, from A$615 million to A$640 million forecast earlier, while cutting its underlying earnings before interest, taxes, depreciation and amortization, or EBITDA, forecast to A$245 million to A$265 million from A$385 million to A$410 million. 

Stock Chart IconStock chart icon

hide content

Shares of NEXTDC on 22 Oct.

The delays to power stem from the suspension of infrastructure upgrades at the company’s M3 Melbourne data center amid community opposition, with electricity distributor Jemena not expecting to resume work before February 2027, according to NextDC.

Jemena cited safety concerns and restricted access to work sites due to community opposition, as well as a lack of consent from the local council pending further community consultation.

Citi said in a note that NextDC’s power delays could affect earnings beyond fiscal 2027, citing delays to approvals for the M3 expansion and a longer-than-expected timeline for transformer upgrades.

Australia welcomes data centres if they ‘contribute to the energy grid’: Treasurer Chalmers

As Australia grapples with growing concerns over the impact of data center developments on local communities, Treasurer Jim Chalmers said the government was working to establish national standards for investment.

Chalmers told CNBC’s “Squawk Box Asia” on Wednesday that the government welcomes investment in data centers and AI infrastructure, provided it aligns with the country’s national interest, adding that the government was finalizing national investment standards to address concerns surrounding AI deployment.

Australia is not alone in facing opposition to data center projects, there has been growing push back against data center developments worldwide, amid concerns over their impact on local communities and the environment.

NextDC shares have declined for seven straight weeks, and are on course to end lower for the eighth week.



Source link